For updates regarding the Bridge Working happening for the next few months please refer to this page. The State will be providing bi-weekly updates that we will post here.
2023 Bridge Work Schedule (updated 4/18/23)
Weekly Construction Update for the week ending 4/16/2023.
Last week, the Contractor removed concrete bridge deck in Spans 2, 4, and 5 and started deck removal in Span 1.
This week, the Contractor is continuing bridge deck removal in Span 1.
- Traffic impacts
- Single lane closure with temporary traffic signals.
For those unfamiliar with the project, the concrete bridge deck will be replaced and widened, to allow for a new, wider sidewalk on the north side of the bridge, new pedestrian and bicycle-friendly traffic barriers, and a new waterline will be installed underneath the bridge between the girders. If you have any concerns or comments, please do not hesitate to contact Dan Doumit (Project Team Lead, 360-430-8869 or Nathan Retherford (Lead Inspector, 360-560-1867)