CR Bridge Work Info.

For updates regarding the Bridge Working happening for the next few months please refer to this page.   The State will be providing bi-weekly updates that we will post here.  

2023 Bridge Work Schedule 

Weekly Construction Update for week ending 3/05/2023.

This week, the Contractor installed Class A signs and started installing containment rigging underneath the bridge. 

Next week, the Contractor is scheduled to start removing bridge diagonal braces with UBIT and continue containment installation.

  • Traffic impacts for next week will consist of a single lane closure with flaggers alternating traffic across the bridge, Monday - Friday.

5 of the 240 total working days have been charged.


For those unfamiliar with the project, the concrete bridge deck will be replaced and widened, to allow for a new, wider sidewalk on the north side of the bridge, new pedestrian and bicycle-friendly traffic barriers, and a new waterline will be installed underneath the bridge between the girders. If you have any concerns or comments, please do not hesitate to contact Dan Doumit (Project Team Lead, 360-430-8869 or Nathan Retherford (Lead Inspector, 360-560-1867)